Its looks that we all are on back to the track of the purpose our friend Bin Ali, provided this plateform to discuss closely the progress of Emirates city.

We are trying our best to report from site and collect datas available from engineer / workers of respective site.. in this process some times we will harsh on the perticular project and even we appreciate their efforts and posatives.
so some one not understand that till yesterday Abou seif contractor was not good how suddenly he is appreciated, we deal with only facts which we can see at site or try to discuss and know the facts about project.

I am very happy to know that now a days we all are adressing the core issues as what we used to do in the past since last 5-6 months this site was guverned by sallers and buyers.

Hope we can cont. feed the progressive and constructive reports from the site.

Inside - Lift area

Its a view from inside the core- whole arrangement lift as unit as you can see and continously they can cast 200mm step by step -

Holding points - Availability of ready mix concrate with pump on continous basis.
Fixing up the steel (reinforcement).

Minimum 40 workers inclusive of skilled and unskilled are required to perform the casting.

More updates - next week

Lavender Block

Dear Dwarish,
Thank you for the time and effort you put in this forum and you helped us a lot, above all your expertise to explain about construction phases and what is involved, it has been great knowledge for me at least.
May I also say thank to all others who are dedicated to help like Imre, Deepineyez, yusuf, djamel and last but not least Bin ali who gave us this opportunity to exchange views, air our concern etc.