Dear Parham and oshurie thanks a lot for timely help... now I can see the Flickers pics.
1. Lavender slipform is on hold as you can see the reinforcement is not erected as its to be done by contractor worker, either they diverted the manpower to other project or they still suffering for required man power
2. As we discussed earlier that minimum 40 - 50 skilled semi skilled workers are required with slip form machenism, but it seems that contractor will pay the heavy rental charges but he will not provide manpower required
3. This delay will further create losses for the contractor and these losses may transfer to construction quality.
I request to all to write them... Time is running out last month I was hoping that with new techniques will lead the progress but once again they disoppointed.
If possible try to visit again the R-Holding office and try to understand the future actions ..
Please help me Flicker is blocked in UAE, and I downloaded as suggested earlier to reach to Flicker... but not suceed... please help me.
I had just passed through yesterday .. and really disappointed to see the progress even with high tech machinary... Its seems they are still struggling without proper man power.
Dear Dwarish,
Having seen Imre's flicker photo's looks they concentrated on the main car park and comparing the above shown photo with imre's one there is no change with slipform, right?.
your comments are highly appreciated, by the way I could not see Lillie for progress with imre's reporting.
Comments
Thanks Parham, Thanks Oshurie
Dear Parham and oshurie thanks a lot for timely help... now I can see the Flickers pics.
1. Lavender slipform is on hold as you can see the reinforcement is not erected as its to be done by contractor worker, either they diverted the manpower to other project or they still suffering for required man power
2. As we discussed earlier that minimum 40 - 50 skilled semi skilled workers are required with slip form machenism, but it seems that contractor will pay the heavy rental charges but he will not provide manpower required
3. This delay will further create losses for the contractor and these losses may transfer to construction quality.
I request to all to write them... Time is running out last month I was hoping that with new techniques will lead the progress but once again they disoppointed.
If possible try to visit again the R-Holding office and try to understand the future actions ..
Couldn't open Flicker
Please help me Flicker is blocked in UAE, and I downloaded as suggested earlier to reach to Flicker... but not suceed... please help me.
I had just passed through yesterday .. and really disappointed to see the progress even with high tech machinary... Its seems they are still struggling without proper man power.
Now its going to be out of control...
Please help me to see the flicker pictures....
Slipform-Lavender
You can see the slipform reached to second floor level its reached to that level within 2 days as we already discussed that 3.5 mtr. can cast everyday
Slipform-Lavender
Dear Dwarish,
Having seen Imre's flicker photo's looks they concentrated on the main car park and comparing the above shown photo with imre's one there is no change with slipform, right?.
your comments are highly appreciated, by the way I could not see Lillie for progress with imre's reporting.