Dear All,
Please see the attached construction status of Majestic towers, Construction of slab # 25 & and gymnasium slab are completed. Swimming pool works are progressing. Air condition ducting, electrical works and fire fighting works (15th floor) are continuing simultaneously with plastering and tiles work. Water tank with proofing has completed in the lower ground.
dear sir ; Where is
dear sir ;
Where is attachment?
No attachment
cany you please send some photos