Construction Updates for Paradise Lakes B2-B9 as of 15th June 2009

Construction Updates for Paradise Lakes B2-B9 as of 15th June 2009

I have uploaded all towers photos at...
http://www.emiratescity.org/category/image-gallery/towers-row-b/b02-09-p...

regards,
Paul

Nads's picture

construction progress

Thank Paul66 for the latest images.
Even though we should be living there by now, it is good to see that there is finally some construction progress with B2 to B5 anyway.
In Apr they were at car parking level 2 on my tower, and now they are on floor 3 residential. Lets see how they go. Don't really want to part with anymore money yet - especially after my pleasantary emails.

Hoepfully its not preceived as a stupid question but is anyone else paying Jul 09 installment. If I don't pay it will be my second missed payment.