Arra open to project cancellation if necessary
By Parag Deulgaonkar on 11/3/2009
Ajman Real Estate Regulatory Agency (Arra) may consider transferring a project to another developer for completion if the original developer has absconded, provided all the parties accept the option, a top government official said.
"Although this is not such a simple decision, we will take a step that is conducive to protecting investors' money. If by doing so we can help both the investor and developer alike, we will do it," Arra Director-General Omar Al Barguthi told Emirates Business.
Asked when Ajman plans to introduce regulations for project cancellations, Al Barguthi said: "Cancellation of a project is not an easy decision. However, the decision to scrap a project can be taken only if it serves the interests of all parties concerned."
Even though failure to open escrow account is a clear violation of the provisions of the Emiri Decree, Arra has extended the deadline in certain cases considering the current situation and the global financial downturn.
What happens to developers who have launched projects before Arra's establishment and have subsequently failed to register with the agency?
All developers should comply with the Emiri Decree No. (8) /2008 and its amendments. Arra will be looking into each case separately and tackle each issue on a case-by-case basis.
Arra has already recommended to Ajman Government to establish a dispute committee that would be entrusted to resolve real estate disputes. The committee is expected to be set up by the end of the year.
The Emiri decree is very clear in this regard. Property developers who failed to register with Arra are not allowed to operate in Ajman, and we shall resort to all possible methods to ensure the law is applied.
Are more developers likely to complete registration by year end?
Yes, developers who started the registration process and could not manage to complete it for reasons beyond their control are expected to complete the registration process.
If a developer starts construction and then abandons it, what action can investors take?
A committee representing Arra, the other developer and investors can be set up to evaluate the situation and stand on the reasons why the work has stopped, and take an action that serves the interests of all parties.
Will Arra transfer the development to some other developer?
Although this is not such a simple decision, we will take a step that is conducive to protecting investors' money. If by doing so we can help both the investor and developer alike, we will do it. Transferring the development to another developer is also an option provided that this option is accepted by all parties concerned.
What punitive measures have you initiated against developers who have failed to open escrow accounts? Any deadline set for them?
Failing to open an escrow account is a clear violation of the provisions of the Emiri Decree. Nevertheless, due to the current situation and the global financial downturn, resulting in a lack of cash flow, deadline has been extended in some cases.
When are you planning to come out a law on cancellation of a project? What major changes will it bring to the market?
Currently, we are looking into each case separately, where we evaluate the situation of the developer, his project and the actual progress on the project as well as the customers' payments made so far.
Cancellation of a project is not an easy decision. However, the decision to scrap a project can be taken only if it serves the interests of all parties concerned.
How many complaints do you receive on a daily basis and what is the major issue concerning investors?
Nature of complaints differs from one investor to another. For example, employees who invested in real estate and lost their jobs usually demand cancellation of their reservations and money back.
Investors languishing under financial burdens are also among the investors who visit Arra's customer service to register their complaints. Delay in construction are some other complaints investors make.
Are you stipulating any action against master developers who have failed to hand over land to sub- developers?
Part of Arra's responsibilities is to make sure provisions of the Emiri Decree are transparently enforced. Master developers who fail to hand over the plots to sub-developers will be held accountable unless acceptable reason for such an act is provided.
Do you believe there will be mergers of master developers in Ajman?
Absolutely. Arra co-ordinates with master and sub- developers. We study all proposals on a case-by-case- basis. Naturally, following the financial meltdown, mergers between small and even giant companies has become a common practice.
As a matter of fact, Arra has on different occasions called for mergers between small developers in Ajman. Therefore, we welcome amalgamation and encourage it among developers.
Arra And lake view
What you think about lake view real estate in Ajman? do you think any positive part coming up for lake view investors? you know the owner of lake view is in jail for frauding.
And the lake view office is keeping quite and they never respond to investors.......they are lying all the time to investors.
ARRA and Ajyaal residency
What you think of Ajyaal residency the owner fled to Pakistan with the investor's money and all his local partner's (From UAE) can't be found for example Ajman Land properties who attended show in London and sold the project to investor's?? any answer to that?
Which city was Ajyaal
Which city was Ajyaal Residence in???
Emirates City
Emirates City
SAT real estate middle east
SAT lake view ,office in twin tower diera dubai. Not responding any e-mail.Every time wrong information for investors.we have lot of questions as every one know the MARMOOKA CITY PROJECTS has been reduced to 20 developers 170 cancelled.when he will refund amount?or he offering another project ? is that project rejister with Ajman real estate regulatory authority.How this authority protecting the investors money.why lake view project not included in ajman regulatory authority list with escrow or without escrow?I am in Canada which is the right department/authority with web/email to make complaint?please any one can help me to write?
Cancellation of Ajyaal Project - Most Simple case for ARRA
It is an open fact that the Ajyaal Residency management was a bunch of cheaters, who fled away and left their investors seeking for justice from the Ajman government. The Director General of ARRA saying that any developer violating the Emiri Decree are liable to the cancellation of their project. In this context, if we look at the Ajyaal Residency Project, they did not complete Registration with ARRA neither got NOC and nor opened an Escrow account, also their bank accounts were sealed by the government. Now what other proofs of default are required.
In my view, this is a straight forward open and shut case for ARRA to cancel this project, there by resolving this pending dispute and refund of payments to investors can be managed through the left over assets of Ajyaal, local partners and sealed bank accounts. This one action will greatly enhance the credibility of ARRA and would also give a positive message to other defaulting developers of EC Ajman.
The same action is needed
The same action is needed for emirates pearls in EC .
wha is arra going to do with
wha is arra going to do with projects & developers which are not register yet? what will happen to such projects investors payments?do they loose their money or the government suport them?
bbc1 watchDog
Hi all Investors in UK
The Watch dog program in BBC1 in British Tv contacted me through my wife in London
The program wants to contact British investors in Ajman, Specially lake view investors.
If any investors want to contact this program please let me know.
Sapphire Lake View Towers - Emirates City
Don't know what is happening with the Sapphire Lake View towers construction.
Can someone update me on this project.
thanks